Ascot Air were contracted to carry out the refurbishment of the existing West wing of the Forgan Smith building at the UQ St Lucia Campus.
Ascot Air were contracted to carry out the base building upgrade of the Jesse Vasey wing, which involved the refurbishment of the Main Central Zone AHU complete with new Chilled Water Coils, 10 No. Plug fans in lieu of the existing centrifugal supply fan. Other services included 2 x New Perimeter AHU’s commissioned to provide 100% outside air with chilled water pipework, steam pipework, controls and commissioning. We also provided booster pumps to the main chilled water plant in the basement of the Jesse Vasey Wing and room upgrade including Variable Air Volume boxes and controls additions.
Details
Client: Shape
Value: $1.0 Mil
Consultant: Part D&C Part Hawkins Jenkins Ross
Services provided
Chilled Water Air Handling Units
BMS Controls Installation
Secondary Chilled Water Booster pumps
VAV upgrade to Bedrooms
Medical Gases
Mechanical Electrical
Chilled Water and Steam Pipework & Thermal Insulation
Testing & Commissioning
10 No. EC Plug fans to replace old Centrifugal supply fan